North Central Florida Swimming Pool Permit Report 2027
Public permit records from three offices, counted the same way: how many new in-ground pools were permitted, where, and how long the City of Gainesville took to issue them.

In 2025, the three permit offices we could measure in North Central Florida took applications for about 515 new residential in-ground pools. That breaks down to 22 inside the City of Gainesville, 93 in unincorporated Alachua County and 400 in unincorporated Marion County. In the City of Gainesville, the median time from application to permit issuance was 56.5 days. Gainesville data runs through July 2026.
Published January 12, 2027 · Last updated January 12, 2027 · Gainesville data through July 2026
Key numbers
- Marion County (unincorporated): 400 new in-ground pool permit applications in 2025, after 406 in 2023 and 408 in 2024. The number has been flat for three years.
- Alachua County (unincorporated): 93 in 2025, down from 106 in 2023.
- City of Gainesville: 22 in 2025. Applications for January to July 2026 total 9.
- Gainesville permit time: a median of 56.5 days from application to issuance (52 permits applied for between January 2024 and July 2026). The middle half took 36 to 72 days.
- For every new in-ground pool applied for inside Gainesville city limits in 2025, unincorporated Marion County took about 18.
How many new pools were permitted in 2023-2025?
The table counts new residential in-ground pool permits by the year the application was filed. It excludes permits that were later voided, cancelled or expired.
| Permit office | Area it covers | 2023 | 2024 | 2025 |
|---|---|---|---|---|
| City of Gainesville | Inside Gainesville city limits | 19 | 23 | 22 |
| Alachua County | Unincorporated Alachua County | 106 | 94 | 93 |
| Marion County | Unincorporated Marion County | 406 | 408 | 400 |
| City of Ocala | Inside Ocala city limits | not yet available | not yet available | not yet available |
Sources: City of Gainesville, Gainesville Permit Cases (snapshot dated July 31, 2026). Alachua County Growth Management, BuildingPermitsCS. Marion County Building Safety, Citizen Self Service. All three were queried on November 17, 2026. Analysis by MR & MRS Outdoor Living.
The three areas are different sizes, so the rows show where pools are being built. They do not rank offices. Most new pools in the region go into unincorporated county land, not inside the two cities. If you are building in Marion County, our Ocala pool builders page covers how we work there. Our custom pool construction page covers the whole region.
How long does a Gainesville pool permit take?
Half of the new residential in-ground pools applied for in the City of Gainesville between January 2024 and July 2026 had their permit issued within 56.5 days of the application date. A quarter were issued within 36 days, and a quarter took 72 days or longer. The fastest took 24 days and the slowest 192.
| Applications filed in | Permits issued | Median days, application to issue |
|---|---|---|
| 2024 | 23 | 50 |
| 2025 | 22 | 58 |
| January 2024 to July 2026 | 52 | 56.5 |
Source: City of Gainesville, Gainesville Permit Cases, fields Application_Date and Issue_Date. Analysis by MR & MRS Outdoor Living.
That clock stops when the permit is issued. It does not include design before the application or construction after it. For the full sequence, see our pool construction timeline in Florida. In practice, the permit is the first thing to start on a Gainesville pool, because nothing goes in the ground before it is issued. Our Gainesville pool builders page explains how we schedule design around it.

Which office issues your permit?
The office is set by the parcel, not by the mailing address. Many homes with a Gainesville or Ocala address sit in unincorporated county land and are permitted by the county. Look up your parcel on the county property appraiser's site and check the jurisdiction or tax district it lists. Our guide to what permits are required for pool construction in Florida covers what each office reviews.
How we measured this
- Sources and dates.
- City of Gainesville: the "Gainesville Permit Cases" table published by the city on ArcGIS. It is a one-time export dated July 31, 2026 and is not refreshed, so Gainesville data runs through July 2026.
- Alachua County: the county's BuildingPermitsCS layer, which is updated continuously. It was last edited on November 17, 2026.
- Marion County: the county's public Citizen Self Service search.
- We queried all three on November 17, 2026.
- What counts.
- Gainesville: permits of subtype "New Swimming Pool".
- Alachua County: permit type "Pool/Spa Permit", subtype "New Construction".
- Marion County: permit type "Residential Swimming Pool / Spa - In-Ground". This type can include in-ground spas permitted on their own, which we cannot separate.
- Gainesville and Alachua County records mix in other kinds of work. We read every work description and removed commercial pools, above-ground pools and stand-alone spas. A pool with an attached spa counts as one pool.
- Excluded. Permits whose status is void, cancelled or expired. Alachua County's records only use "expired" among those statuses.
- Geography.
- We checked every Gainesville permit counted for 2023 to July 2026 (91 in all, including the 9 from 2026) against the city's current boundary map. All 91 fall inside it.
- Of the Alachua County permits counted for 2023-2025, one now falls inside Gainesville city limits.
- Smaller cities with their own building departments are not included, nor is the City of Ocala.
- Time. "Days to permit" is the number of calendar days between the application date and the issue date the office recorded. We only report it for Gainesville. The counties record their own dates, and we have not confirmed that "application date" means the same step in every office.
- Privacy. We publish counts only. No addresses, owners, contractors or permit numbers.
- What this cannot tell you. It does not tell you how long your own pool will take. It does not show which office is faster. It does not say why counts went up or down.
In Gainesville and Ocala
We build pools on both sides of this table, inside city limits and on county land. Before design starts, we check which office has your parcel, because that decides the review, the inspections and the calendar. Start with our Gainesville pool builders page or our Ocala pool builders page. If you are still early, read before you build a pool in Florida.
Cite this report
You are welcome to reuse these figures with credit. A link is appreciated but not required.
MR & MRS Outdoor Living. North Central Florida Swimming Pool Permit Report 2027. Published January 12, 2027. https://www.mrandmrsoutdoorliving.com/blogs/north-central-florida-pool-permit-timeline-report
Sources
- City of Gainesville, Gainesville Permit Cases, table All_Permit_Cases (export dated July 31, 2026).
- City of Gainesville, Gainesville_Boundary, city limits used for the geography check.
- Alachua County Growth Management, BuildingPermitsCS.
- Marion County Building Safety, Citizen Self Service, permit type Residential Swimming Pool / Spa - In-Ground.
Plan your pool
If your parcel is in Gainesville, Alachua County, Ocala or Marion County, we can tell you which office will review it and what that means for your schedule. Request a design-build evaluation.
Common questions
Which office issues my pool permit in Gainesville or Ocala?
It depends on whether your parcel sits inside city limits. Inside the City of Gainesville or the City of Ocala, the city's building department issues it. In unincorporated Alachua or Marion County, the county does. Your property appraiser record shows which jurisdiction your parcel is in.
How long does it take to get a pool permit in Gainesville?
In the City of Gainesville, half of the new residential in-ground pool permits applied for between January 2024 and July 2026 were issued within 56.5 days of the application date. A quarter took 72 days or longer.
Does the permit time include building the pool?
No. The figure runs from the date the city logged the application to the date it issued the permit. Excavation, inspections and finishing all come after that.
Why is there no figure for the City of Ocala?
The City of Ocala's permit portal does not allow the kind of bulk public query we used for the other three offices. We will add Ocala once the records arrive through a public records request.
Sources
About the author
Robert Wesley Brannen is the co-founder of Mr. & Mrs. Outdoor Living and a Florida-certified pool and spa contractor. Having started in his family's aluminum business at age 13 and previously led Happy House Outdoor Living, Robert brings extensive experience in custom pool construction, outdoor structures, and design-build project management.
Florida Licenses: CPC1460562 · CPC1461119 · SCC131153553.
Most Read Articles

What Permits Are Required for Pool Construction in Florida?
A new inground pool in Florida needs a building permit from your city or county, with electrical and plumbing work covered under it, a set sequence of inspections, and a safety barrier that passes before the final. Here is what each piece is, who issues it and what slows it down.Read More: What Permits Are Required for Pool Construction in Florida?
Pool Construction Timeline in Florida: What to Expect From Start to Finish
A Florida pool is built in a fixed order of phases, and the calendar is set by what each phase waits on: the permit, the weather, an inspection, or a cure time. Here is every phase in sequence, what gates it, and where the time actually goes.Read More: Pool Construction Timeline in Florida: What to Expect From Start to Finish
Before You Build a Pool in Florida: 12 Decisions to Make Before Excavation
Once the excavator arrives, some decisions stop being decisions. These are the twelve worth settling first, and which of them are genuinely hard to undo.Read More: Before You Build a Pool in Florida: 12 Decisions to Make Before Excavation